The Niwot Sanitation District’s wastewater plant reconstruction is making impressive strides, with multiple projects advancing simultaneously. From truss installation on the UV building to water testing in the Oxidation Ditch, each phase brings the facility closer to completion. Crews are diligently installing trusses, pouring concrete, and backfilling critical infrastructure like the new gravity…
Layouts - Landing Page #3
News & Events
What's New
This month at the Niwot Sanitation District Waste Water Treatment Plant, we've made significant strides. The clarifier and scum pit are complete, with the clarifier ready for water to be sterilized in our new UV building before release into Dry Creek. The Headworks project is advancing with CMU installation, plumbing, and electrical work nearly finished. The Anaerobic Digester passed its water…
Significant strides have been made in the new Niwot Sanitation District plant. The Oxidation Ditch is seeing progress with elevated deck installations and water testing of the anaerobic selector. The Dewatering Building is being sealed for upcoming water tests. Meanwhile, the Clarifier is undergoing major installations including decking and piping. The Headworks Building has completed its…
- Accordion title 1
-
Accordion content 1.
- Accordion title 2
-
Accordion content 2.
- Accordion title 3
-
Accordion content 3.
Text Block
Suspendisse rutrum quis felis in ullamcorper. Praesent non viverra felis. Aenean id pulvinar orci. Vestibulum sollicitudin fringilla elit non placerat.