The Niwot Sanitation District’s wastewater plant reconstruction is making impressive strides, with multiple projects advancing simultaneously. From truss installation on the UV building to water testing in the Oxidation Ditch, each phase brings the facility closer to completion. Crews are diligently installing trusses, pouring concrete, and backfilling critical infrastructure like the new gravity main crossing Dry Creek. Join us as we dive into the latest updates on the UV building, Headworks, dewatering building, clarifiers, and more, showcasing the progress transforming this vital community project.
Our office remains open during regular hours — Monday through Friday from 9:00 AM to 3:00 PM.
Truss Installation Begins for UV Building Construction
Rice Lake West construction crews are actively installing trusses over the new UV building as part of the ongoing development project.
Trusses and Weather Guard Installed, Ready for Metal Sheeting
The UV building construction has progressed with the trusses and weather guard fully installed, and the structure is now awaiting the installation of metal sheeting to complete the roofing process.
Headworks Progress: CMU Installed, Roof Slab Poured, and Ready for Trusses and Roofing
The Headworks building is steadily taking shape with the CMU walls now fully installed and looking impressive. The roof slab pour has been completed, setting the stage for the installation of trusses and roofing, which is scheduled to begin in the next few weeks.
Dewatering Building Passes Water Tests, Deck Poured for Next Construction Phase
The dewatering building has successfully passed its water tests, and the decking has been poured, making it fully prepared for the next stage of the construction process.
Oxidation Ditch Undergoes Water Testing, WAS and RAS Building Prepares for Next Concrete Pour
The Oxidation Ditch is currently undergoing water testing to ensure functionality, while the WAS and RAS building forms have been set and are prepared for the next concrete pour in the construction process.
Clarifier Construction Advances with Backfilling for Plug and Patch Phase
The clarifier construction is progressing as the backfilling process continues, preparing the structure for the upcoming plug and patch phase.
New Gravity Main Installed, Crosses Dry Creek
The new gravity main has been successfully installed and has now crossed Dry Creek, marking a significant milestone in the Niwot Sanitation District’s wastewater plant reconstruction.
What's next?
Here’s a look at the upcoming milestones for the project:
The Headworks will undergo caulking, a framing inspection for the roof, followed by roof installation and insulation.
The UV building is scheduled for exterior joint caulking, ceiling installation, and insulation.
For the Clarifier, equipment will be coated with UV-resistant paint, and the hoist bridge and tower will be installed.
The Oxidation Ditch will continue water testing through May, with additional tasks including forming pipe encasements, installing the RAS WAS header, completing underground electrical work, and setting RAS WAS rebar and concrete. Lastly, the Aerobic Digester, also known as the Dewatering Building, is set for rebar installation, electrical work, and a concrete pour in the coming month.