Oxidation Ditch Progress: Elevated Decks and Anaerobic Selector Testing Underway
The Oxidation Ditch has most of the forms in place, and rebar installation for the elevated decks is underway. The anaerobic selector is currently undergoing water testing, and we are eager to see the results.
Dewatering Building Prepares for Crucial Water Tests with Ongoing Sealing Efforts
The dewatering building continues to be patched and sealed in preparation for upcoming water tests.
Clarifier Undergoes Major Installations
The Clarifier is having its elevated decking installed, with a 3-inch scum line and a 14-inch effluent line being connected. Backfilling around the clarifier and the A-basin shoring wall is also underway.
Headworks Building Progresses with Underslab Piping Completion and Backfilling
The headworks building is being backfilled, and the underslab piping has been completed.
Headworks UV Building Reaches Milestone: CMU Work Complete, Awaiting Further Development
The Headworks UV building is progressing well; all CMU blocks have been laid and grouted, setting the stage for the next phase of construction.
What's next?
Over the coming weeks, significant progress will be made at RLW, though the visual impact might be less striking as most buildings and concrete structures are already in place. Starting January, we'll update this blog monthly, with the next update scheduled for January 31st, 2025, considering the holiday season.
The upcoming tasks include:
- Headworks: Expect more rebar installation, electrical work, rebar inspections, concrete pouring, form stripping, insulation, and CMU construction.
- Clarifier: Shoring will be removed, backfilling will continue, rebar for the trough will be installed and inspected, troughs will be poured, and strip bridge brackets will be set up.
- Oxidation Ditch: The final wall on the inner ring will be installed, the elevated deck will be formed, rebar will be placed and inspected, electrical work will begin, the anaerobic tank will be backfilled, and there might be concrete pouring if weather permits.
- Aerobic Digester: The plug and patch work will be completed, and we aim for a water test by month's end.
We appreciate your engagement with our blog this year. Stay tuned for more updates from RLW and JVA in January 2025. Enjoy the holidays, and see you next year!