Our office remains open during regular hours — Monday through Friday from 9:00 AM to 3:00 PM.
Clarifier and Scum Pit Completion
Above, you can see the clarifier with a freshly poured trough. This is where the clarified water will exit the clarifier to be sterilized in our new UV building before being released into Dry Creek. Additionally, the scum pit is complete, and all plumbing has been installed.
Headworks Progress Update
The Headworks project is progressing well; CMU installation is underway, and both plumbing and electrical work are nearing completion. There are just a few small concrete pours remaining, and most of the backfill has already been completed.
Anaerobic Digester Passes Water Tests, RLW Begins Elevated Deck Construction
The Anaerobic Digester underwent water testing after the plug and patching were completed in January. All water tests passed, and now RLW is beginning work on the elevated deck.
Oxidation Ditch Construction Advances: RLW Completes Grating and Elevated Deck Work
Our Oxidation Ditch is advancing as well. RLW has installed the grating, poured the elevated deck, and is now allowing it to cure. The process took longer than expected due to the cold weather and the precision needed to ensure the elevated decking was flawless.
Above is a panoramic view of the Niwot Sanitation District Waste Water Treatment Plant, lightly dusted with snow.
What's next?
In the upcoming month at the headworks, we plan to install shoring and rebar. Weather permitting, we aim to pour concrete during the first week of March. For the UV building, truss installation and roof construction are scheduled to begin in the same week. Our Clarifier will continue to be backfilled as the surrounding work progresses. At the Oxidation Ditch, RLW will remove the shoring, initiate pier work, cast piers, and proceed with RAS/WAS grading and slab work throughout the rest of February.
The Aerobic Digester is set for the installation of elevated decking, rebar, and concrete pouring by the first week of March. RLW will also start pier work for the dewatering slab and continue setting pipes while backfilling the area. Lastly, RLW will collaborate with JVA to place engineered fill, install pipe encasement, lay pipe to cross Dry Creek, and set up a new manhole to connect to our new headworks.