Our office remains open during regular hours — Monday through Friday from 9:00 AM to 3:00 PM.
Headworks Progress: Walls Up, Slabs Poured
The Headworks project is progressing well, with additional walls constructed and several slabs poured. Electrical and plumbing installations are also underway. While a few sections remain to be completed, RLW is delivering excellent work.
Contact Chamber Progress: First CMU Blocks in Place
The Contact Chamber, which will soon house our UV building, is beginning to take shape with brickwork and the installation of CMU (Concrete Masonry Units). CMUs, precast rectangular blocks commonly used for walls, foundations, and other structures, are featured prominently here. We’ve captured both a top view and a side view of the progress. While these blocks will be utilized throughout the construction site, this marks their first application in this project.
Clarifier Passes Tests; RLW Begins Backfilling and Shoring Removal
The Clarifier has successfully passed all water tests, and the scum pit formation is complete. RLW is now backfilling and removing the earth shoring simultaneously as they backfill and compact the soil.
Oxidation Ditch Decking Expanded; Water Test for Anaerobic Selector Planned
The elevated decking for the Oxidation Ditch has been further expanded. The anaerobic selector (covered area) is being prepared for a water test, which is anticipated to take place next week.
Final Touches Underway on Aerobic Digester and Dewatering Building Ahead of Water Test
The aerobic digester and dewatering building has had all its walls poured, and RLW is now completing the finishing touches in preparation for an upcoming water test.
What's next?
Next week at the headworks, RLW will be backfilling the electrical room and beginning the underslab plumbing. The UV Building will continue with the construction of CMU walls. At the clarifier, water testing of the scum box will take place, followed by backfilling and the continued removal of earth shoring. In the Oxidation Ditch, RLW will proceed with installing elevated deck shoring and forms. Water testing will begin for the anaerobic tank, with backfilling scheduled once it passes. The Dewatering Building and Aerobic Digester will continue preparations for water testing next year. Weather permitting, vacuum testing of the gravity main and manholes will take place.
Thank you for reading this update. We hope you and your loved ones had a wonderful holiday!