Progress Advances on Dewatering Building: Aerobic Digester Tanks Poured and Curing Underway
Significant progress has been made on the Dewatering building, with concrete pours and forms advancing well. The aerobic digester tanks within the building have been poured and will harden over the next few days. Black tarps have been placed as blankets to retain heat, and heaters are used as needed, depending on temperatures, to ensure optimal concrete curing.
Headworks Project Advances with Wall Pouring
The Headworks project is making excellent progress this week. RLW has completed pouring all the walls and has applied protective blankets to ensure the curing process proceeds uninterrupted despite the cold weather.
Oxidation Ditch Anaerobic Tank Nears Next Milestone
The Oxidation Ditch anaerobic tank is beginning to take shape with forms and rebar in place. The team is working diligently to complete the next concrete pour as soon as possible.
Clarifier Forms Set for Scum Pit as RLW Prepares for Upcoming Pour
The Clarifier forms are being set for the scum pit, and RLW is preparing for the upcoming scum pit pour.
What's next?
Next week at the Headworks, we’ll be installing more rebar and have several concrete pours scheduled. The Clarifier will see its final pour for the scum pit. The Oxidation Ditch will have a few more concrete pours, completing the radius walls, and we’ll begin installing the elevated deck shoring/forms for the ditch. We look forward to updating you next week!