Our office remains open during regular hours — Monday through Friday from 9:00 AM to 3:00 PM.
Progress on Dewatering Building as Workers Pour Walls and Install Forms
Above is a distant photo of the Dewatering Building, taken from afar to ensure safety due to active cranes in the area. Additional walls have been poured, and forms have been installed. This week, workers concentrated on this area to protect concrete pours from the effects of the cold weather.
Headworks Building Nears Completion of Form and Rebar Installation Ahead of Next Pour
The Headworks building has more forms installed and finishing rebar installation before our next pour.
Niwot Implements Anaerobic Treatment
We began placing forms in the anaerobic tank, a sealed environment that fosters anaerobic bacteria. These bacteria thrive without oxygen, breaking down organic matter into biogas, including methane, carbon dioxide, hydrogen, hydrogen sulfide, nitrogen, and water vapor. For Niwot, this enables us to treat phosphorus and meet new regulatory requirements. Regulation 85, a monitoring program, limits phosphorus and nitrogen in plant effluent. This initiative will help reduce greenhouse gas emissions and minimize odor as well.
Gravity Line and Non-Portable Lines Nearly Complete
Our gravity line and non pot line are 80% finished we are glad this is ready for future tie-in to our main and headworks.
RLW Prioritizes Dewatering Building Amid Snow and Cold Temps
The Clarifier has been drained, but due to the snow, low temperatures, and the resulting mud, RLW focused on the dewatering building this week.
What's next?
Next week, weather permitting, RLW is scheduled for a total of eight pours. One will be at the clarifier for the scum pit, while three pours at the Oxidation Ditch will complete the radius walls throughout the ditch. Additionally, two pours are planned for the dewatering building to form future walls. As long as the weather holds up, it looks like a productive week ahead.