Our office remains open during regular hours — Monday through Friday from 9:00 AM to 3:00 PM.
Headworks Structure Prepped for Next Phase
The photos above show the rebar and wall forms installed around the headworks structure, fully prepared for the next pour day.
Clarifier Passes Water Test, Scum Pit Construction Set to Begin
The clarifier has successfully passed its water test and is now ready for the installation of scum pit forms and rebar. Weather permitting, we aim to complete the scum pit by the end of the week.
Rice Lake West Completes Major Milestone Before First Frost
The oxidation ditch’s main walls have been poured — marking a major accomplishment for Rice Lake West in completing these large concrete sections ahead of the first frost.
First Walls Poured for Dewatering Building
Shown above is the first set of walls poured for the dewatering building, with forms and rebar being installed for additional pours over the coming days.
Gravity Main and Non-Potable Lines Near Completion
The gravity main and non-potable lines are nearly complete, with backfilling and manhole invert installation now underway. This will raise the new manholes above ground level to prevent infiltration from ground and surface water.
What's next?
Next week, we will be pouring the wall forms for the Headworks. The Oxidation Ditch requires two small pours to complete the interior ring. In the Clarifier, we will set the rebar and forms for the scum pit and proceed with backfilling. More walls for the Dewatering building will also be formed and poured. Additionally, installation and backfilling of gravity lines and non-potable lines will continue. Please note that all activities are contingent on weather conditions and temperatures during next week's construction.