Construction of the new sanitation plant continued to make steady progress this week. The new headworks building now includes completed pipes, rebar, and wall forms after a recent concrete pour. The clarifier began water testing, while the oxidation ditch neared completion. A new manhole connected to the future gravity main, and the dewatering building prepared for upcoming pours.
Our office remains open during regular hours — Monday through Friday from 9:00 AM to 3:00 PM.
Headworks Progress: Pipes and Rebar Set, Concrete Pour Complete with Wall Forms Installed
The first picture of the Headworks shows all the pipes and rebar in position, ready for the concrete pour. The second photo captures the completed pour, with some wall forms already installed.
Clarifier Water Test Begins: Rare View of Basin Before Final Backfill and Scum Pit Installation
Above, we see the water test beginning for the Clarifier. This is the only opportunity we will have to observe the bottom of the clarifier with water in it. The backfill we discussed last week will occur later, as we still need to form and pour the scum pit.
Oxidation Ditch Nears Completion: Walls Set with Few Sections Remaining
The oxidation ditch is really taking shape this week, with nearly all the walls set and formed, leaving only a few sections to complete.
New Manhole Installed for Gravity Main to Headworks, Groundwater Managed with Multi-Hose Setup
Another manhole has been installed and connected to the future gravity main that will feed into the headworks. Rice Lake West has been working diligently to keep groundwater out of this area, given the clay layers in the soil. As you can see, multiple hoses are being used to manage the water.
Dewatering Building Progress: Forms and Rebar Set for Upcoming Pours
The dewatering building has more forms and rebar installed, preparing for future concrete pours.
Beautiful Views from Niwot Sanitation
Here’s another stunning view of the project as the seasons change.
What's next?
The headworks will have forms and rebar installed for the surrounding walls. At the clarifier, Rice Lake West will set forms, install rebar for the trough, and remove shoring and backfill as needed. The Oxidation Ditch will continue with final wall section form-setting, while the attached Aerobic Digester will have rebar wrapped with forms and the first wall poured. Finally, Rice Lake West will continue laying the gravity main and installing manholes.